Issue - meetings

Highway Maintenance and Local Initiative Report - Huntley Rd

Meeting: 09/08/2018 - Central Stockport Area Committee (Item 7)

7 Highway Maintenance and Local Initiative Report - Huntley Road, Cheadle Heath pdf icon PDF 87 KB

To consider a report of the Corporate Director for Place Management and Regeneration

 

The report sets out a proposal for a footway resurfacing scheme on Huntley Road from Edgeley Road to Sherbourne Road.

 

The Area Committee is requested to approve the maintenance scheme outlined in the report and authorise the Corporate Director for Place Management and Regeneration to order the week.

 

Officer Contact: Simon Sherry on 0161 474 2420 or email: simon.sherry@stockport.gov.uk

Additional documents:

Minutes:

A representative of the Democratic Services Manager submitted a report of the Corporate Director for Place Management and Regeneration (copies of which had been circulated) setting out a proposal for a footway resurfacing scheme on Huntley Road from Edgeley Road to Sherbourne Road, Cheadle Heath.

 

RESOLVED – That the footway resurfacing scheme on Huntley Road from Edgeley Road to Sherbourne Road, Cheadle Heath be approved at an approximate cost of £8,500 to be funded from the Area Committee’s Delegated Budget (Edgeley and Cheadle Heath Ward allocation).