Issue - meetings

Progress in Delivering the Stockport Homes, Stockport Council and Viaduct Partnership Development Programme

Meeting: 22/11/2017 - Stockport Housing Commission (Item 5)

5 Progress in Delivering the Stockport Homes, Stockport Council and Viaduct Partnership Development Programme pdf icon PDF 247 KB

To consider a report of the Director of Resources, Stockport Homes.

 

On 8 March 2017 a full progress report was delivered to the Housing Commission which included the full details of the development programme, including details of individual schemes. This report provides an update on the previous report.

 

The Commission is recommended to comment on and note the report.

 

Officer contact: Steve Leonard on 0161 474 3460 or email: steve.leonard@stockporthomes.org

Additional documents:

Minutes:

A representative of the Director of Resources, Stockport Homes submitted a report (copies of which had been circulated) providing an update on progress in delivering the Stockport Homes, Stockport Council and Viaduct Partnership Development Programme.

 

It was reported that since the previous report the total number of completed new build homes (including those under construction) had increased from 535 units to 725 units.

 

The following comments were made:-

 

·         During the first quarter, the ‘Cross Keys’ scheme had been completed which offered 14 homes for rent, and tenants had moved into the properties in May.

·         A further two schemes had commenced during Quarter 1 at the ‘Bredbury Curve’ and St Thomas’ Hospital.

·         The development at Blackstone Fields, Offerton had gained planning permission and aimed to provide 27 homes.  Further work was taking place in relation to the land to the rear of the development to better understand the ground conditions.

 

The Chair commented that the progress made to date was encouraging and the outlook for future developments as part of the scheme remained positive.

 

RESOLVED – That the report be noted.


Meeting: 19/07/2017 - Stockport Housing Commission (Item 5)

5 Progress in Delivering the Stockport Homes, Stockport Council and Viaduct Partnership Development Programme pdf icon PDF 243 KB

To consider a report of the Director of Resources, Stockport Homes.

 

On 8 March 2017 a full progress report was delivered to the Housing Commission which included the full details of the development programme, including details of individual schemes. This report provides an update on the previous report.

 

The Commission is recommended to comment on and note the report.

 

Officer contact: Steve Leonard on 0161 474 3460 or email: steve.leonard@stockporthomes.org

Additional documents:

Minutes:

A representative of the Director of Resources, Stockport Homes submitted a report (copies of which had been circulated) providing an update on progress in delivering the Stockport Homes, Stockport Council and Viaduct Partnership Development Programme.

 

It was reported that since the previous report the total number of completed new build homes (including those under construction) had increased from 535 units to 725 units.

 

The following comments were made:-

 

·         During the first quarter, the ‘Cross Keys’ scheme had been completed which offered 14 homes for rent, and tenants had moved into the properties in May.

·         A further two schemes had commenced during Quarter 1 at the ‘Bredbury Curve’ and St Thomas’ Hospital.

·         The development at Blackstone Fields, Offerton had gained planning permission and aimed to provide 27 homes.  Further work was taking place in relation to the land to the rear of the development to better understand the ground conditions.

 

The Chair commented that the progress made to date was encouraging and the outlook for future developments as part of the scheme remained positive.

 

RESOLVED – That the report be noted.