Issue - meetings

DEDICATION OF BRIDLEWAY ON LAND OWNED BY THE COUNCIL, AND CREATION OF A FOOTPATH ON A SECTION OF WILKINSON ROAD, HEATON NORRIS, AS SHOWN ON THE PLAN ATTACHED AT APPENDIX 1.

Meeting: 09/03/2017 - Central Stockport Area Committee (Item 7)

7 DEDICATION OF BRIDLEWAY ON LAND OWNED BY THE COUNCIL, AND CREATION OF A FOOTPATH ON A SECTION OF WILKINSON ROAD, HEATON NORRIS, AS SHOWN ON THE PLAN ATTACHED AT APPENDIX 1. pdf icon PDF 84 KB

To consider a joint report of the Corporate Director for Place Management and Regeneration

 

The report asks the Area Committee to consider whether to dedicate a bridleway over a section of land at Wilkinson Road, Heaton Norris and on an unnamed path that links with Church Road, as shown on the plan attached to the report.

 

The Area Committee is recommended to:-

 

(i)        Authorise the dedication of a bridleway over the section of the route between points A – B - C, as shown on the plan at Appendix 1.

 

(ii)       Authorise the dedication of a footpath over the section of the route between points B – D, as shown on the plan at Appendix 1.

 

(iii)      Authorise the making of a footpath creation order in respect of the section of the route between points D – E, as shown on the plan at Appendix 1.

 

Officer Contact: Ernest Nama on 0161 474 4595 or email: ernest.nama@stockport.gov.uk

Additional documents:

Minutes:

A representative of the Democratic Services Manager submitted a report of the Corporate Director for Place Management and Regeneration (copies of which had been circulated) requesting the Area Committee to consider whether to dedicate a bridleway over a section of land at Wilkinson Road, Heaton Norris and on an unnamed path that linked with Church Road, as shown on the plan attached to the report.

 

RESOLVED – (1) That the dedication of a bridleway over a section of the route between points A-B-C, as shown on the plan at Appendix 1 to the report, be approved.

 

(2) That the dedication of a footpath over the section of the route between points B-D, as shown on the plan at Appendix 1 to the report, be approved.

 

(3) That the making of a footpath creation order in respect of the route between points D-E, as shown on the plan at Appendix 1, be approved.