Issue - meetings

Bruntwood Park Depot Improvement Works

Meeting: 02/04/2013 - Executive (Item 14)

14 Bruntwood Park Depot Improvement Works (GCS13) pdf icon PDF 41 KB

To consider a report of the Executive Councillor (Governance & Corporate Services)

 

The report seeks approval for the implementation of improvement works to Bruntwood Park operational depot and the necessary funding required to complete the project.

 

The Executive is asked to approve the works to be undertaken at Bruntwood Park Depot, and that the remaining capital receipt is released to fund relevant works and that additional funding requirement from Public Realm and Property Reserves be utilised for the purpose of Bruntwood Park Depot.

 

Officer contact: Murray Carr, 0161 474 3649, murray.carr@stockport.gov.uk

Minutes:

The Executive Councillor (Governance & Corporate Services) submitted a report (copies of which had been circulated) inviting the Executive Meeting to approve improvement works to Bruntwood Park Operational Depot and the allocation of the necessary funding required to complete the project. The proposal followed on from the decisions made by the Executive in relation to the disposal of the former Torkington Park Depot and the proposal to make Bruntwood Park Depot an operational hub for Public Realm/ Solutions SK activity in the West of the borough

 

RESOLVED – That

 

·         the proposed improvement works at Bruntwood Park depot be approved;

·         in line with the decision of the Executive in January 2012 in relation to the disposal of the former Torkington Depot, the remaining capital receipt from the sale of that facility be released to fund relevant works and that the additional funding requirement from Public Realm and Property Reserves be utilised for the works at Bruntwood Park Depot.


Meeting: 11/03/2013 - Corporate, Resource Management & Governance Scrutiny Committee (Item 12)

12 Bruntwood Park Depot Improvement Works pdf icon PDF 26 KB

To consider a report of the Corporate Director for Corporate and Support Services.

 

The report invites the Scrutiny Committee to comment upon the proposed improvement works to Bruntwood Park operational depot and the necessary funding required to complete the project.

 

This proposal will be considered by the Executive at the meeting on 2 April 2013.

 

The Scrutiny Committee is invited to comment on the proposed works to be undertaken at Bruntwood Park Depot, and in line with the January 2012 Executive report, the remaining capital receipt being released to fund relevant works and that additional funding requirement from Public Realm and Property Reserves be utilised for the purpose of Bruntwood Park Depot.

 

Officer contact Murray Carr on telephone number 0161 474 3649 or alternatively email murray.carr@stockport.gov.uk

Minutes:

The Corporate Director for Corporate and Support Services submitted a report (copies of which had been circulated) inviting the Scrutiny Committee to comment upon the proposed improvement works to the Bruntwood Park operational depot and the necessary funding required to complete the project.

 

It was reported that the report would be considered by the Executive at its meeting on 2 April 2013.

 

RESOLVED – (1) That the proposed works to be undertaken at the Bruntwood Park Depot be noted.

 

(2) That the Corporate Director for Corporate and Support Services be requested to confirm whether it was intended to improve the condition of the access road to the depot and whether the number of park vehicles using the road was likely to increase.