Decision Maker: Executive Councillor (Communities & Sustainability)
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: Yes
The Executive Councillor (Communities &
Sustainability) has approved the legal advertising of the following
traffic regulation order and subject to no objections being
received the order being made, at an estimated cost of
£600,000 to be funded by the Greater Manchester Cycle City
Ambition Grant:
Revocation Of No Waiting Restriction Monday – Saturday 8am
– 6pm
Newbridge
Lane – North Side, from a point 111 metres
south-east of the projected South-Easterly kerb line of
Millgate, North-Easterly arm of the
roundabout (or from the south-easterly endpoint/extent of
Millgate, South-Easterly arm of the
roundabout) to a point 33m west of the projected Westerly kerb line
of Alpine Road (a distance of approximately 378 metres).
Millgate (South-Easterly Arm of the Roundabout) – North-easterly Side, from a point 14 metres south-east of the projected South-Easterly kerb line of Millgate, North-Easterly arm of the roundabout, for a distance of 97 metres (or to the south-easterly endpoint/ extent of Millgate).
Newbridge Lane – South Side, from
a point 128.5 metres south-east of the projected South-Easterly
kerb line of Millgate, Westerly arm of
the roundabout (or from the south-easterly point/ extent of
Millgate, South-Easterly arm of the
roundabout) to the Westerly kerb line of Bateson Street (a distance
of approximately 313 metres).
Millgate
(South-Easterly Arm of the Roundabout) –
South-westerly Side, from a point 26.5 metres south-east of the
projected Southerly kerb line of Millgate, Westerly arm of the roundabout, for a
distance of 102 metres (or to the south-easterly endpoint/ extent
of Millgate).
Newbridge
Lane – South Side, from a point 15 metres west
of the Westerly kerb line of Alpine Road for a distance of
approximately 63 metres in a westerly direction.
Proposed No Waiting at Any Time Restrictions
Newbridge Lane – North
Side, from a point 111 metres south-east of the projected
South-Easterly kerb line of Millgate,
North-Easterly arm of the roundabout (or from the south-easterly
point/ extent of Millgate,
south-easterly arm of the roundabout) to a point 33m west of the
projected Westerly kerb line of Alpine Road (a distance of
approximately 378metres).
Millgate
(South-Easterly Arm of the Roundabout) –
North-easterly Side, from a point 14 metres south-east of the
projected South-Easterly kerb line of Millgate, North-Easterly arm of the roundabout for
a distance of 97 metres (or to the south-easterly point/ extent of
Millgate.
Newbridge
Lane – South Side, from a point 128.5 metres
south-east of the projected South-Easterly kerb line of
Millgate, Westerly arm of the
roundabout (or from the south-easterly point/ extent of
Millgate, South-Easterly arm of the
roundabout) to the Westerly kerb line of Bateson Street (a distance
of approximately 313 metres).
Millgate
(South- Easterly Arm of the Roundabout) –
South-westerly Side, from a point 26.5 metres south-east of the
projected Southerly kerb line of Millgate, Westerly arm of the roundabout, for a
distance of 102 metres (or to the south-easterly endpoint/ extent
of Millgate).
Newbridge
Lane – South Side, from a point 15 metres west
of the Westerly kerb line of Alpine Road for a distance of
approximately 63 metres in a westerly direction.
Proposed Moving Traffic Regulation Order
Schedule
The following areas of Footway/ Verge are to be converted into a
Cycle Track under Section 65(1) of the Highways Act 1980 so to provide a Shared-Use or Segregated Cycle/ Pedestrian facility:
Newbridge
Lane – North Side, from a point 111 metres
south-east of the projected South-Easterly kerb line of
Millgate, North-Easterly arm of the
roundabout (or from the south-easterly point/ extent of
Millgate, south-easterly arm of the
roundabout) to the westerly side of St Mary’s Way.
Millgate (South-Easterly Arm of the Roundabout) – North-easterly Side, from the projected South-Easterly kerb line of Millgate, North-Easterly arm of the roundabout for a distance of 111 metres (or to the south-easterly point/ extent of Millgate.
Newbridge
Lane – South Side, from a point 24 metres east
of the Easterly kerb line of Bateson Street to the westerly side of
St Mary’s Way.
Millgate
(South-Easterly Arm of the Roundabout) –
South-westerly Side, from the projected Southerly kerb line of
Millgate, Westerly arm of the
roundabout, for a distance of 87 metres in a south-easterly
direction, to and including the frontage of St Mary’s
Gate.
Corporation Street – West side, from the
southerly kerb line of Warren Street to the northerly kerb line of
the Westerly arm of Millgate
roundabout.
Millgate
(Westerly Arm of the Roundabout) – Both sides
and the pedestrian refuge island, from the westerly kerb line of
Corporation Street for a distance of 10 metres in a westerly
direction.
Warren Street – South side, from the westerly
kerb line of Corporation Street for a distance of 28 metres in a
westerly direction.
Proposed Toucan Crossing Facilities Schedule
Newbridge Lane –
Approximately 46 metres (centre of crossing point) east
of
the easterly kerb line of Bateson Street.
Millgate
(South-Easterly Arm of the Roundabout) –
Conversion from a PUFFIN – Approximately 41.5 metres (centre
of crossing point) southeast of the projected southerly kerb line
of the Westerly arm of Millgate
roundabout.
The Central Stockport Area Committee supported the
proposals.
None
Wards Affected: Brinnington & Central;
Decision Reference: EMDCS77
Declarations or conflicts of Interest: None
Contact: Nick Whelan, Services to Place Email: nick.whelan@stockport.gov.uk Tel: 0161-474-4907 Graham Price, Services to Place Email: graham.price@stockport.gov.uk Tel: 0161 474 4893.
Publication date: 22/04/2015
Date of decision: 21/04/2015
Effective from: 29/04/2015
Accompanying Documents: