08/10/2020 - Central Stockport Infrastructure Delivery Plan and Stockport Station Growth prospectus (E&R49 and E&R54/ SS14)

The Cabinet considered the Central Stockport Infrastructure Delivery

Plan Prospectus and Stockport Growth Prospectus along with a general rail update and has:-

 

(1) Endorsed the contents of the Central Stockport Infrastructure Delivery Plan Prospectus and the Stockport Station Growth Prospectus.

 

(2) Agreed that officers should continue to work with TfGM and Network Rail as a priority to explore and identify a new layout and design solution for the Greek Street bridge and the Thomson Street footbridge

 

(3) Noted the proposed stakeholder engagement plan outlined at 4.1 in the report