The AMP capital plan is a rolling upgrade and
improvement programme for the Council's operational buildings. This
report outlines the proposed schemes for the three year period
commencing 2016/17 and seeks approval for those schemes identified
for 2016/17. It also provides an update on progress of the 2015/16
schemes previously approved.
Decision type: Key
Reason Key: Significant expenditure or savings;
Decision status: Recommendations Approved
Wards affected: (All Wards);
Notice of proposed decision first published: 14/01/2016
Decision due: 16 Feb 2016 by Executive
Lead member: Executive Councillor (Support & Governance)
Lead director: Corporate Director (Corporate and Support Services) and Deputy Chief Executive
Department: Corporate and Support Services
Contact: Murray Carr, Corporate and Support Services Email: murray.carr@stockport.gov.uk Tel: 0161-474-3019.
Consultation process
Consultation has been undertaken with the
Strategic Property Alliance, Carillion Stockport Property Services
and key stakeholders such as service providers.
Forward Plan Reference: SG19
Equality and/or Environmental Impact Assessment: Equality and environmental impact assessments will be carried out wherever applicable.
Relevant Scrutiny Committee for the purpose of call-in: Corporate, Resource Management & Governance