Road Safety Around Schools - North Cheshire Jewish Primary School

30/10/2023 - Road Safety Around Schools - North Cheshire Jewish Primary School

At its meeting on 29 November 2022, the Cheadle Area Committee gave approval to the introduction of a number of measures to improve road safety around North Cheshire Jewish Primary School, including the advertisement of a package of associated traffic regulation orders.

 

Following the publication of the decision, it has become apparent that there was an anomaly in the ‘School Keep Clear’ traffic regulation order schedule relating to the location and incorrect item measurements on the drawing. This, if not rectified, could lead to difficulties in enforcement as well as in the mapping of the orders on the Council’s systems.

 

The Cabinet Member for Parks, Highways & Transport Services, following consultation with ward councillors, has given approval to the revocation of the original traffic regulation orders, and to the advertisement of the following revised package of traffic regulation orders and subject to the receipt of no objections within 21 days of the advertisement date, the subsequent making of the orders:-

 

Revocation of Existing Traffic Regulation Orders

 

No Waiting At Any Time

 

St Ann’s Road North (Western Side) - From a point 17m north of the intersection of the northern kerbline of Grasmere Road to a point 17m south of the intersection of the southern kerbline of Grasmere Road

 

Grasmere Road (Both Sides) - From the intersection of the western kerbline of St Ann’s Road North for a distance of 15m in a westerly direction.

 

St Ann’s Road North (Western Side) - From a point 17.5m north of the intersection of the northern kerbline of Oakdale Drive to a point 17.5m south of the intersection of the southern kerbline of Oakdale Drive.

 

Oakdale Drive (Western Side) - From the intersection of the western kerbline of St Ann’s Road North for a distance of 16m in a westerly direction.

 

No Stopping Monday-Friday, 8am-5pm on School Keep Clear Markings

 

St Ann’s Road North (Western Side) - From a point 2m north of the projected southern kerbline of Grasmere Road for a distance of 26.5m in a southerly direction.

 

St Ann’s Road North (Western Side) - From a point 6.5m north of the projected northern kerbline of Oakdale Drive for a distance of 39m in a southerly direction.

 

Proposed Traffic Regulation Order Schedule

 

No Waiting At Any Time

 

St Ann’s Road North (Western Side) - From a point 17m north of the intersection of the northern kerbline of Grasmere Road to a point 17m south of the intersection of the southern kerbline of Grasmere Road

 

Grasmere Road (Both Sides) - From the intersection of the western kerbline of St Ann’s Road North for a distance of 15m in a westerly direction.

 

St Ann’s Road North (Western Side) - From a point 17.5m north of the intersection of the northern kerbline of Oakdale Drive to a point 17.5m south of the intersection of the southern kerbline of Oakdale Drive.

 

Oakdale Drive (Western Side) - From the intersection of the western kerbline of St Ann’s Road North for a distance of 16m in a westerly direction.

 

No Stopping Monday-Friday, 8am-5pm on School Keep Clear Markings

 

St Ann’s Road North, (East side): From a point 1 metre North-East of the projected Southern kerb line of Grasmere Road in a South-Westerly direction for a distance of 25.56 metres.

 

St Ann’s Road North, (East side): From a point 6 metres North-East of the projected Northern kerb line of Oakdale Drive (Northern junction), in a South-Westerly direction for a distance of 43.56 metres.


30/11/2022 - Road Safety Around Schools - North Cheshire Jewish Primary School

The Area Committee has given approval to the proposals for the Road Safety around Schools – North Cheshire Jewish Primary School scheme:

 

·         the legal advertising of the Traffic Regulation Orders set out in Appendix A to the report (Drawing No 0305/63/NC/002), and subject to no objections being received within 21 days from the advertisement date, the subsequent making of the orders; and

 

·         implementation of dropped kerbs, 20mph roundels (road markings) and provision of new school warning signs.

 

To be funded from the Road Safety around Schools programme budget allocation.