DC/077459 - Belmont House, Schools Hill, Cheadle

Partial demolition, refurbishment and conversion of currently vacant listed building, Belmont House, to 4 no. residential apartments and 1 no. residential townhouse. Plus erection of new build elements comprising: 7 no. residential apartments, 3 no. 3 storey residential townhouses and 2 no. 2 storey residential townhouses, plus additional landscaping and amenity spaces. Total of 17 no. new residential units.

 

The Area Committee is recommended to grant planning permission, subject to:-

 

·         Conditions

·         The applicant entering into a Section 106 Agreement to:

-       Secure a phasing strategy for the repairs/restoration of Belmont House;

-       To ensure that should the scheme become viable in the future, that developer contributions can be sought at that time; and

-       Secure developer contributions towards the ‘No Waiting At Any Time’ restrictions proposed.

 

·         No new substantive issues being raised by an extended public notification period explained at the beginning of the report.

 

Officer Contact: Rebecca Whitney on 0161 474 4405 or email: rebecca.whitney@stockport.gov.uk

Minutes:

In respect of plan no. DC/077459 for the partial demolition, refurbishment and conversion of currently vacant listed building, Belmont House, to 4 no. residential apartments and 1 no. residential townhouse. Plus erection of new build elements comprising: 7 no. residential apartments, 3 no. 3 storey residential townhouses and 2 no. 2 storey residential townhouses, plus additional landscaping and amenity spaces. Total of 17 no. new residential units at Belmont House, Schools Hill, Cheadle, it was

 

RESOLVED – That the Planning and Highways Regulation Committee be recommended togrant planning permission, subject to:-

 

·         Conditions

·         The applicant entering into a Section 106 Agreement to:

-       Secure a phasing strategy for the repairs/restoration of Belmont House;

-       To ensure that should the scheme become viable in the future, that developer contributions can be sought at that time; and

-       Secure developer contributions towards the ‘No Waiting At Any Time’ restrictions proposed.

 

·         No new substantive issues being raised by an extended public notification period explained at the beginning of the report.

 