7 Highways Maintenance and Local Initiative Report Battersbay Grove PDF 305 KB
To consider a report of Deputy Chief Executive & Corporate Director for Place Management & Regeneration.
The report details a proposed highway maintenance scheme on Battersbay Grove, Hazel Grove – Carriageway Resurfacing (Part Contribution) totalling £9,750.00.
The Area Committee is recommended to approve the maintenance scheme outlined in the report and authorise the Deputy Chief Executive & Corporate Director for Place Management & Regeneration to order the work, at a cost of £9,750.00 to be funded from the Area Committee’s Delegated Budget (Hazel Grove Ward Allocation).
Officer contact: Simon Sherry on 0161 474 2420 or email: simon.sherry@stockport.gov.uk
Additional documents:
Minutes:
A representative of the Strategic Head of Service (Legal & Democratic Governance and Monitoring Officer) submitted a report of the Deputy Chief Executive & Corporate Director for Place Management & Regeneration (copies of which had been circulated) detailing a proposal to resurface the carriageway of Battersbay Grove, Hazel Grove and that the Area Committee be requested to make a partial contribution of £9,750 to the total cost of the scheme from its Delegated Budget.
It was commented that the proposal represented a successful compromise following discussions with the Council Highways Team and that part-funding of the works would avoid consuming the totality of the delegated budget.
RESOVLED – (1) That approval be given to the resurfacing of the carriageway of Battersby Grove, Hazel Grove, with the Area Committee making a part contribution totalling £9,750.00, to be funded from the Area Committee’s Delegated Budget (Hazel Grove Ward Allocation).
(2) That the Deputy Chief Executive & Corporate Director for Place Management & Regeneration be authorised to order the work.