14 Heaton Norris Park - Delegated Ward Budget PDF 96 KB
To consider a report of the Corporate Director for Place Management and Regeneration
The report sets out proposed resurfacing works and play area improvements in Heaton Norris Park.
The Area Committee is recommended to approve the maintenance scheme outlined in the report and authorise the Corporate Director for Place Management and Regeneration to order the work.
Officer Contact: Richard Booker on 0161 474 4829 or email: richard.booker@stockport.gov.uk
Additional documents:
Minutes:
A representative of the Deputy Chief Executive submitted a report of the Corporate Director for Place Management and Regeneration (copies of which had been circulated) setting out details of a proposed scheme to mitigate a developing issue with tree root damage in Heaton Norris Park Play Area and in doing so make play area improvements.
RESOLVED – That approval be given to the maintenance scheme outlined in the report at an approximate cost of £19,000 to be funded as follows:-
- £17,000 from Stockport Homes and Section 106 Commuted Sums for Play
- £2,000 from the Area Committee’s Delegated Budget (Brinnington and Central Ward allocation).
(2) That the Corporate Director for Place Management and Regeneration be authorised to order the work.