Cherry Close - Footway Scheme

Meeting: 17/04/2018 - Stepping Hill Area Committee (Item 9)

9 Cherry Close - Footway Scheme pdf icon PDF 86 KB

To consider a report of the Corporate Director for Place Management & Regeneration.

 

The report sets out a proposal to install footway on Cherry Close, Offerton.

 

The Area Committee is invited to approve the installation of footway opposite nos.1 and 3 Cherry Close at a cost of £2300 to be funded from the Highway Delegated Budget.

 

Officer contact: Alan Whitfield, 0161 474 3255, alan.whitfield@stockport.gov.uk

Additional documents:

Minutes:

A representative of the Democratic Services Manager submitted a report of the Corporate Director for Place Management & Regeneration (copies of which had been circulated) inviting the Area Committee to consider a proposal to install a selection of footway on Cherry Close, Offerton.

 

RESOLVED – That approval be given to installation of a section of footway opposite no.s 1 and 3 Cherry Close, Offerton at a cost of £2,300 to be funded from the Area Committee’s delegated budget (Offerton Ward allocation)