8 Highways Maintenance and Local Initiative Scheme - Reddish Vale Road PDF 90 KB
To consider a report of the Corporate Director for Place Management and Regeneration.
The report requests the Area Committee to consider Drainage Work on Reddish Vale Road following the proposed Local Initiative Scheme.
The Area Committee are requested to consider the proposals detailed in the report.
Officer Contact: Chris Pollitt on Tel: 474 2419 or email: chris.pollitt@stockport.gov.uk
Minutes:
A representative of the Corporate Director for Place Management and Regeneration submitted a report (copies of which had been circulated) requesting the Area Committee to consider the installation of a 25m single sized stone drainage channel and x2 new gulley grate and frames, connecting one to an existing chamber to alleviate the current problem of water flowing across the carriageway.
RESOLVED – That the installation of a 25m single sized stone drainage channel and x2 new gulley grate and frames, connecting one to an existing chamber to alleviate the current problem of water flowing across the carriageway to be funded at an approximate cost of £1,750 to be funded via the Area Committee delegated budget (to be divided equally between the four wards) be approved.