Issue - meetings

Kirkstead Road Area, Cheadle Hulme

Meeting: 07/08/2014 - Bramhall & Cheadle Hulme South Area Committee (Item 9)

9 Kirkstead Road Area, Cheadle Hulme pdf icon PDF 49 KB

To consider a report of the Corporate Director for Place Management & Regeneration.

 

The report sets out the results of consultation on proposals to introduce waiting restrictions and physical measures in the Kirkstead Road area of Cheadle Hulme  seeks following concerns raised by residents about road safety.

 

The Area Committee is recommended to approve the proposals set out in the report.

 

Officer contact: Andrew Varey; 0161 474 4809;  andrew.varey@stockport.gov.uk

Additional documents:

Minutes:

The Democratic Services Manager submitted a report (copies of which had been circulated) of the Corporate Director for Place Management & Regeneration setting out the results of consultation on proposals to introduce waiting restrictions and physical measures in the Kirkstead Road area of Cheadle Hulme  seeks following concerns raised by residents about road safety.

 

RESOLVED - That the proposed introduction of No Waiting at Any Time on restrictions on the following roads as set out below be approved at a cost of £4,450 be funded from the Area Committee’s Highway Maintenance and Traffic Management Delegated Budget (Cheadle Hume South Ward allocation):

 

Fountains Road, Cheadle Hulme, north side, from a point 7 metres west of the westerly kerb line of Kirkstead Road for a distance of 5 metres in a westerly direction.

 

Fountains Road, Cheadle Hulme, north side, from a point 40 metres east of the easterly kerb line of Kirkstead Road for a distance of 20 metres in an easterly direction.

 

Fountains Road, Cheadle Hulme (Service Road adjacent to No. 58b), west side, from the northerly kerb line of Fountains Road for a distance of 11 metres in a northerly direction.

 

Fountains Road, Cheadle Hulme (Service Road adjacent to No. 58b), east side, from the northerly kerb line of Fountains Road for a distance of 15 metres in a northerly direction.

 

Kirkstead Road, Cheadle Hulme, east side, from a point 5 metres north of the northerly kerb line of the Fountains Road Service Road for a distance of 13 metres in a southerly then easterly direction (into Fountains Road Service Road).

 

Yew Tree Park Road, Cheadle Hulme, east side, from a point 9 metres north of the northerly kerb line of Kirkstead Road for a distance of 6.5 metres in a northerly direction.

           

(2) That the Proposed Civil Engineering Worksas set out below be approved:

 

Kirkstead Road, Cheadle Hulme – construction of in-line dropped crossing with tactile paving.

 

Kirkstead Road, Cheadle Hulme, build-up of existing redundant dropped kerb to prevent vehicles accessing footway, install Morpeth Bollard adjacent to remaining existing dropped crossing.

 

Yew Tree Park Road, Cheadle Hulme, construction on in-line dropped crossing (no tactile paving).