22 Adlington Walk Future High Streets Fund (C&H38/ E&R89) PDF 242 KB
To consider a report of the Cabinet Member for Economy & Regeneration.
The report provides an update on progress relating to the delivery of Stockroom and seeks Cabinet approval to delegate entering into a build contract and additional finance in light of construction inflationary pressures.
(NOTE: The report contains ‘not for publication’ appendices that have been circulated to the Cabinet only).
The Cabinet is recommended to note the contents of the report and appendices and approve:-
(1) The additional financial commitment from the Council to progress with the project,
(2) Endorse the headline offer and overall vision for Stockroom and the benefits to the Council and the people of Stockport this will bring
(3) Delegate approval to the Director of Development and Regeneration and the Deputy Chief Executive in consultation with the Cabinet Member for Economy and Regeneration to enter into contract with the contractor to build Stockroom for a target cost of £13.5m
(4) Authorise the Assistant Director (Legal & Democratic Governance) to do all things necessary to enter into contract with the contractor.
Officer contact: Robert Goulsbra on 0161 218 1764 or email: robert.goulsbra@stockport.gov.uk.
Additional documents:
Minutes:
The Cabinet Member for Economy & Regeneration (Councillor Colin MacAlister) submitted a report (copies of which had been circulated) providing an update on progress relating to the delivery of Stockroom and proposals to seek Cabinet approval to delegate entering into a build contract and additional finance in light of construction inflationary pressures.
(NOTE: The report contained ‘not for publication’ appendices that had been circulated to the Cabinet only).
RESOLVED - (1) That approval be given to the additional financial commitment from the Council to progress with the project as detailed in the report.
(2) That the headline offer and overall vision for Stockroom and the benefits to the Council and the people of Stockport this will bring be endorsed.
(3) That authority be delegated to the Director of Development and Regeneration and the Deputy Chief Executive in consultation with the Cabinet Member for Economy and Regeneration to enter into contract with the contractor to build Stockroom for a target cost of £13.5m
(4) That authority be delegated the Assistant Director (Legal & Democratic Governance) to do all things necessary to enter into contract with the contractor.
14 Adlington Walk Future High Streets Fund PDF 414 KB
To consider a report of the Director of Development and Regeneration.
The report provides an update on progress relating to the delivery of Stockroom and seeks Cabinet approval to delegate entering into a build contract and additional finance in light of construction inflationary pressures.
The Scrutiny Committee is requested to note the contents of the report and provide comments to Cabinet.
Officer contact: Robert Goulsbra | robert.goulsbra@stockport.gov.uk
Additional documents:
Minutes:
A representative of the Director of Development and Regeneration submitted a report (copies of which had been circulated) providing an update on progress relating to the delivery of Stockroom and sought Cabinet approval to delegate entering into a build contract and additional finance in light of construction inflationary pressures.
RESOLVED – That the report be noted.