Issue - meetings

Mayor's Cycling and Walking Challenge Fund - Bee Network Crossings - Broadstone Road

Meeting: 17/10/2022 - Heatons & Reddish Area Committee (Item 11)

11 Mayor's Cycling and Walking Challenge Fund - Bee Network Crossings - Broadstone Road pdf icon PDF 265 KB

To consider a report of the Director of Place Management.

 

The report provides the results of a consultation on the Mayor’s Challenge Fund (MCF) Bee Network Crossing proposals to provide a new signalised junction on Broadstone Road at the junction with Broadstone Hall Road South and Broadstone Hall Road North, with new pedestrian and cycle crossing facilities (Toucan crossings) on all arms, with associated parking restrictions.

 

The Area Committee is asked to comment on the proposal and recommend that the Cabinet Member (Economy & Regeneration) approves the implementation of the scheme and the legal advertising of the Traffic Regulation Orders set out in Appendix C, and subject to no objections being received within 21 days from the advertisement date, the subsequent making of the orders at an approximate cost of £400,000 to be funded (subject to the approval of the business case by Transport for Greater Manchester) from the MCF Capital fund.

 

Officer contact: Nick Whelan on 0161 474 4907 or email: nick.whelan@stockport.gov.uk

Additional documents:

Minutes:

A representative of the Director for Place Management submitted a report (copies of which had been circulated) providing the results of a consultation on the Mayor’s Challenge Fund (MCF) Bee Network Crossing proposals to provide a new signalised junction on Broadstone Road at the junction with Broadstone Hall Road South and Broadstone Hall Road North, with new pedestrian and cycle crossing facilities (Toucan crossings) on all arms, with associated parking restrictions.

 

Members welcomed the report

 

RESOLVED – That the Cabinet Member (Economy & Regeneration) be recommended to approve the implementation of the scheme and the legal advertising of the Traffic Regulation Orders set out in Appendix C of the report, and subject to no objections being received within 21 days from the advertisement date, the subsequent making of the orders at an approximate cost of £400,000 to be funded (subject to the approval of the business case by Transport for Greater Manchester) from the MCF Capital fund.


Meeting: 12/09/2022 - Heatons & Reddish Area Committee (Item 11.)

11. Mayor's Cycling and Walking Challenge Fund - Bee Network Crossings - Broadstone Road pdf icon PDF 265 KB

To consider a report of the Director for Place Management.

 

The report provides the results of a consultation on the Mayor’s Challenge Fund (MCF) Bee Network Crossing proposals to provide a new signalised junction on Broadstone Road at the junction with Broadstone Hall Road South and Broadstone Hall Road North, with new pedestrian and cycle crossing facilities (Toucan crossings) on all arms, with associated parking restrictions.

 

The Area Committee is asked to comment on  and recommend that the Cabinet Member (Economy & Regeneration) approves the implementation of the scheme and the legal advertising of the necessary Traffic Regulation Orders and subject to no objections being received within 21 days from the advertisement date the order can be made.

 

Officer contact: Nick Whelan, 0161 474 4907 or email nick.whelan@stockport.gov.uk

Additional documents: