Issue - meetings

Mayor's Cycling and Walking Challenge Fund - Bee Network Crossings - Edgeley Road

Meeting: 04/08/2022 - Central Stockport Area Committee (Item 9)

9 Mayor's Cycling and Walking Challenge Fund - Bee Network Crossings - Edgeley Road pdf icon PDF 862 KB

To consider a report of the Director of Place Management.

 

To report the results of a consultation on the Mayor’s Challenge Fund (MCF) Bee Network Crossing proposals to provide a new signalised junction on Edgeley Road at Northgate Road/ Edgeley Fold, new ‘green man’ pedestrian crossing facilities at the existing signal junction of Edgeley Road/ Dale Street, plus some associated new parking restrictions and amendments to access controls in the area.

 

The Area Committee is requested to consider the proposals and recommend that the Cabinet Member (Economy & Regeneration) approves the implementation of the scheme and the legal advertising of the necessary Traffic Regulation Orders at Appendix A, and subject to no objections being received within 21 days from the advertisement date, the order be made (to be funded (subject to the approval of the business case by Transport for Greater Manchester) from the MCF Capital fund).

 

Contact officer: Nick Whelan 0161 474 4907 | nick.whelan@stockport.gov.uk

Additional documents:

Minutes:

A representative of the Director for Place Management submitted a report of the (copies of which had been circulated) detailing the results of a consultation on the Mayor’s Challenge Fund (MCF) Bee Network Crossing proposals to provide a new signalised junction on Edgeley Road at Northgate Road/ Edgeley Fold, new ‘green man’ pedestrian crossing facilities at the existing signal junction of Edgeley Road/ Dale Street, plus associated new parking restrictions and amendments to access controls in the area.

 

Thanks were expressed to officers for securing the crossing on Dale Street.

 

RESOLVED – That the Cabinet Member (Economy & Regeneration) be recommended to approve the implementation of the scheme and the legal advertising of the necessary Traffic Regulation Orders at Appendix A, and subject to no objections being received within 21 days from the advertisement date, that the order be made (to be funded from the MCF Capital fund, subject to the approval of the business case by Transport for Greater Manchester).