Decision Maker: Executive
Decision status: Recommendations approved
Is Key decision?: Yes
Is subject to call in?: Yes
Executive approval and Formal Adoption of the SPD
The Executive Meeting considered the final draft of the Woodford Aerodrome Opportunity Site Supplementary Planning Document (SPD) which set out the environmental, social, design and economic objectives relevant to and which would guide development and use of land at the site within the boundary of Stockport. The SPD had been subject to consultation with local residents and interested parties, as well as the Bramhall & Cheadle Hulme South Area Committee, the Planning & Highways Regulation Committee and the Environment & Economy Scrutiny Committee.
The Executive Meeting then approved the Woodford Aerodrome Opportunity Site Supplementary Planning Document (SPD) as part of the Stockport Local Development Framework, subject to the following amendments:-
· Under paragraph 2.8, replace reference to Avro 718 with Avro 748
· Under paragraph 5.10, replace existing text with “The Council has considered three principal options for the approach to the distribution of development on the site each of which could be delivered in accordance with relevant development plan policies so as to meet identified needs in terms of, for example, housing mix, density, open space and play provision. Any pattern of development proposed in a planning application will be required to demonstrate that it is in general conformity with all relevant development plan policies or that other material considerations exist which justify a departure from those policies. The options are represented diagrammatically as the following three concepts:”
The Executive considered a recommendation of the Bramhall & Cheadle Hulme South Area Committee from 10 December 2012 that the SPD be deferred to allow for a further consultation on the final document. The Executive agreed that sufficient consultation had already been undertaken and that to delay further the adoption of the SPD would hinder the Council in determining any future planning application.
None
Wards Affected: Bramhall South & Woodford;
Equality and/or Environmental Impact Assessment: Not required
Decision Reference: ED1471
Forward Plan Reference: RGN193
Other reasons / organisations consulted
Environment & Economy Scrutiny
Bramhall & Cheadle Hulme South Area Committee
Planning & Highways Committee
Contact: Paul Lawrence, Services for Place Email: paul.lawrence@stockport.gov.uk Tel: 0161-474-4515.
Report author: Paul Lawrence
Publication date: 16/01/2013
Date of decision: 14/01/2013
Decided at meeting: 14/01/2013 - Executive
Effective from: 23/01/2013