Decision Maker: Cabinet
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: Yes
To provide an update on the background and
progress of the scheme to replace Greek Street rail Bridge in
Stockport
The Cabinet has considered a report providing an update on progress with the scheme to replace the Greek Street bridge and the options being considered, and has:-
(1) Approved delegation of authority to the Deputy Chief Executive, in consultation with the S151 Officer and the Cabinet Member for Economy and Regeneration approval to enter into a delivery agreement with Network Rail to progress optioneering, appraisal and design of the enhanced option, the estimated cost is up to £0.5m to be funded by Transforming Cities Fund 2.
(2) Approved Council officers to work with officers from TfGM to seek approval for an appropriate release of development funding including from the identified £7m Transforming Cities Fund 2.
None.
None.
Reason Key: Affects 2 or more wards;
Wards Affected: Brinnington & Central; Edgeley & Cheadle Heath;
Equality and/or Environmental Impact Assessment: yes
Decision Reference: CAB310
Declarations or conflicts of Interest: None.
Forward Plan Reference: E&R66
Other reasons / organisations consulted
portfolio holder, CLT, E
Contact: Mark Glynn, Director of Place Management Email: mark.glynn@stockport.gov.uk Tel: 0161-474-3700.
Report author: Amy Beasley
Publication date: 01/07/2021
Date of decision: 29/06/2021
Decided at meeting: 29/06/2021 - Cabinet
Effective from: 08/07/2021