A6 To Manchester Airport Relief Road Scheme Phase Two Consultation Update And General Progress Report (EDR17)

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To inform the Executive of the results of the second phase of consultation on the proposed A6 to Manchester Airport Relief Road scheme.

 

Decision:

The Executive Meeting considered an update on progress of the second phase of the consultation on the A6 to Manchester Airport Relief Road Scheme and the proposed next stages in the development of the scheme and has agreed that

 

(i)      the report be noted and support the on-going work to develop the final preferred scheme for future approval by the promoting authorities; and

(ii)     support be given to the submission of planning application for associated work at Styal Golf Club and the oil terminal pipeline if necessary.

Alternative options considered:

None

Interests and Nature of Interests Declared:

None

Wards Affected: Bramhall South & Woodford; Cheadle Hulme South; Hazel Grove; Heald Green; Marple South & High Lane;

Equality and/or Environmental Impact Assessment: Yes

Decision Reference: ED1538

Forward Plan Reference: EDR17

Other reasons / organisations consulted

2nd phase public consultation on the scheme will run from 3 June to 19 July 2013.

Contact: Sue Stevenson, Services to Place Email: sue.stevenson@stockport.gov.uk Tel: 0161-474-4351.

Report author: Sue Stevenson

Publication date: 14/08/2013

Date of decision: 13/08/2013

Decided at meeting: 13/08/2013 - Executive

Effective from: 21/08/2013