A6 to Manchester Airport Relief Road Scheme - Update Report on Procedural Issues. (EDR13)

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To consider an update about the on-going procedural work to develop the scheme including updates on land acquisition, Section 8 agreements between the promoting authorities and policy on compensation and land acquisition.

 

This issue is connected to previous decisions on this scheme available at: http://democracy.stockport.gov.uk/mgIssueHistoryHome.aspx?IId=9628&Opt=0

 

 

Decision:

The Executive Meeting considered a report on the various work streams required to support the development of the A6 to Manchester Relief Road Scheme, and agreed that

 

·         the A6 to Manchester Relief Road Scheme Draft Section 8 Agreement at Appendix 1 be approved and that the authority to enter into the Section 8 Agreement be delegated to the Chief Executive in consultation with the Executive Councillor (Economic Development & Regeneration) to finalise the terms with Cheshire East Council and Manchester City Council;

·         the A6 to Manchester Relief Road Scheme Procurement Strategy at Appendix 2 be approved and that the process for appointing a contractor be approved, including delegating approval of the short list of potential contractors to the Chief Executive in consultation with the Executive Councillor (Economic Development & Regeneration) following the PQQ process and requesting Executive approval of the proposed contractor following the ITT process;

·         the proposed Land Acquisition Strategy and compensation approach set out in the report be approved; and

·         authority be delegated to the Project Director of the A6 to Manchester Airport Relief Road in consultation with the Chief Finance Officer the ability to approve the purchase of plots of land required for the scheme subject to the cost being accommodated within the overall budget allocation for land acquisition.

Alternative options considered:

None

Interests and Nature of Interests Declared:

None

Wards Affected: Bramhall North; Bramhall South & Woodford; Cheadle Hulme South; Hazel Grove; Heald Green; Marple South & High Lane;

Equality and/or Environmental Impact Assessment: Undertaken as part of overall scheme.

Decision Reference: ED1497

Forward Plan Reference: EDR13

Other reasons / organisations consulted

Consultation has been undertaken with partners (Cheshire East and Manchester City councils)

Contact: Sue Stevenson, Services to Place Email: sue.stevenson@stockport.gov.uk Tel: 0161-474-4351.

Report author: Jim McMahon

Publication date: 03/04/2013

Date of decision: 02/04/2013

Decided at meeting: 02/04/2013 - Executive

Effective from: 10/04/2013