Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
The report provides an update on the delivery
of the A6MARR scheme and the associated decisions required to
complete the delivery of the scheme.
The Cabinet considered an update on the outcome of discussions with contractors for the A6-Manchester Airport Relief Road in relation to concerns about the scheme costs and delivery and agreed that
· the content of the report be noted and approval be given to the proposed settlement with Morgan Sindall.
· the Corporate Director for Place Management & Regeneration and the Head of Legal & Democratic Governance, in consultation with the Cabinet Member for Economy and Regeneration, be authorised to finalise the settlement agreement and take all necessary steps to bring it into effect.
(Note: the report included a ‘not for publication’ appendix that had been circulated to cabinet members only).
None
Wards Affected: (All Wards);
Equality and/or Environmental Impact Assessment: Undertaken as part of the scheme development
Decision Reference: CAB123
Declarations or conflicts of Interest: None
Other reasons / organisations consulted
CLT, Scrutiny and Cabinet
Contact: Sue Stevenson, Services to Place Email: sue.stevenson@stockport.gov.uk Tel: 0161-474-4351.
Report author: Emily Brough
Publication date: 03/10/2018
Date of decision: 02/10/2018
Decided at meeting: 02/10/2018 - Cabinet
Effective from: 10/10/2018