Decision details

A6 to Manchester Airport Relief Road - Proposed Compulsory Purchase Orders and Side Road Orders submission

Decision Maker: Chief Executive

Decision status: Recommendations approved

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

Approving the preferred scheme for submission of planning application and approval of submission of planning application.

Decision:

In accordance with the Executive’s decision of 1 October 2013, the Chief Executive, in consultation with the Executive Councillor (Economic Development and Regeneration) has approved the following in relation to the Compulsory Purchase Orders and Side Road Orders needed for A6 to Manchester Airport Relief Road Scheme:-

 

Being satisfied that all necessary measures have been put in place and that the Metropolitan Borough Council of Stockport (in its own behalf and acting as agent for Cheshire East Borough Council and Manchester City Council under the provisions of an agreement under Section 8 of the Highways Act 1980), approval is hereby given for -

 

1.    the Council Solicitor to make and submit to the Secretary of State for Transport for confirmation, a Side Roads Order under Sections 8, 14 and 125 of the Highways Act 1980 and all other powers enabling them in that behalf, in relation to the proposed construction of a new classified A6, Hazel Grove, Stockport  to Manchester Airport relief road, designed to improve, stop up and construct lengths of highway and to stop up and provide new means of access to premises to support the proposed construction of the relief road and

 

2.    that pursuant to the aforementioned authority to make a Side Roads Order, the Council Solicitor to make and submit to the Secretary of State for Transport for confirmation an Order under Sections 8, 239, 240, 246, 250 and 260 of the Highways Act 1980 and all other powers enabling them in that behalf, to purchase compulsorily the land and new rights contained within the attached plan and shown coloured pink and blue and described below for the purpose of -  

           

a)    the construction of a highway from a point on the new length of the A6 Buxton Road, Stockport  to be constructed between Yew Tree Lane, Stockport and Norbury Hollow Road, Stockport extending generally westwards to a point on the A555 Manchester Airport Eastern Link Road 520 metres west of the A5102 Woodford Road, Bramhall, Stockport;

b)    the improvement of the A555 Manchester Airport Eastern Link Road from its junction with the A5102 Woodford Road, Bramhall, Stockport to its junction with the B5338 Wilmslow Road, Handforth, Cheshire;

c)    the construction of a highway from a point on the A555 Manchester Airport Eastern Link Road 356 metres east of the B5338 Wilmslow Road, Handforth, Cheshire extending generally westwards, to a point on Ringway Road in Wythenshawe, Manchester, 200 metres east of the junction of Ringway Road with Ringway Road West;

d)    the construction, improvement and diversion of highways and the provision of new means of access to premises in the Metropolitan Borough of Stockport, in the City of Manchester and in the Parishes of Poynton-with-Worth, Handforth, and Styal, in the Borough of Cheshire East;

e)    the diversion of watercourses and the execution of other works on watercourses in connection with the construction and improvement of highways and the execution of other works mentioned above;

f)     use by the Metropolitan Borough Council of Stockport in connection with such construction and improvement of highways and the execution of other works mentioned above; and

g)    the mitigation of any adverse effects which the existence or use of the highways proposed to be constructed or improved will have on their surroundings;

h)   to enter to construct, inspect and maintain the works mentioned above.

 

3.         The Council Solicitor to apply to the Secretary of State for Communities and Local Government for a Certificate pursuant to Section 19(1)(a) of the Acquisition of Land Act 1981 to authorise the Metropolitan Borough Council of Stockport to acquire land used for public recreation and needed to facilitate the proposed relief road in exchange for land which is no less in area and equally advantageous as the land taken.

Alternative options considered:

Detailed consideration and discussion with affected landowners has taken place to optimise the land required for the scheme.

Interests and Nature of Interests Declared:

None

Wards Affected: Bramhall South & Woodford; Cheadle Hulme South; Hazel Grove; Heald Green; Marple South & High Lane;

Equality and/or Environmental Impact Assessment: Yes

Decision Reference: ODCE7

Forward Plan Reference: EDR18

Other reasons / organisations consulted

2nd phase public consultation on the scheme will run from 3 June to 19 July 2013.

Contact: Sue Stevenson, Services to Place Email: sue.stevenson@stockport.gov.uk Tel: 0161-474-4351.

Publication date: 29/11/2013

Date of decision: 27/11/2013

Accompanying Documents: