Decision details

Appointment of a contractor for the A6 to Manchester Airport Relief Road (EDR24)

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approve the appointment of a contractor for the A6 to Manchester Airport Relief Road following the procurement process.

Decision:

The Executive Meeting considered a report on progress with appointing a contactor to develop the design and construct the proposed A6 to Manchester Airport Relief Road and have agreed that:-

 

(1) progress with the appointment of contractor be noted and the process used be approved;

 

(2) the Chief Executive, in consultation with the Executive Councillor (Economic Development & Regeneration) be authorised to appoint the contractor and make other ancillary decisions and legal agreements with the organisation ‘A’ as set out in the Exempt Appendix to the report.

 

(Note: the report contained information ‘not for publication’ contained within its appendix that had been circulated to executive councillors only).

Alternative options considered:

None

Interests and Nature of Interests Declared:

None

Reason Key: Affects 2 or more wards;

Wards Affected: Bramhall South & Woodford; Cheadle & Gatley; Hazel Grove; Heald Green; Marple South & High Lane;

Equality and/or Environmental Impact Assessment: Equality Impact Assessment undertaken as part of the scheme development

Decision Reference: ED1553

Forward Plan Reference: EDR24

Other reasons / organisations consulted

Not applicable.

Contact: Jim McMahon, Services to Place Email: jim.mcmahon@stockport.gov.uk Tel: 0161-474-4800.

Publication date: 02/10/2013

Date of decision: 01/10/2013

Decided at meeting: 01/10/2013 - Executive

Effective from: 09/10/2013